Part of power plant's transmission line could go underground
By: JOSE CARVAJAL - Staff Writer | ∞
LAKE ELSINORE ---- The latest plan for a high-voltage transmission line that would serve a proposed hydroelectric power plant in the hills southwest of the lake calls for a segment of the line to be buried underground, federal administrators said Thursday.
That would eliminate the risks posed by the transmission line to hang gliders, who say the area is a world-renowned hotbed for the sport.
"We are claiming this as a victory for hang gliding," Elsinore Hang Gliding Association representative Ken Niemi said Thursday. "It seems that (Federal Energy Regulatory Commission) has recognized this. It seems they're doing something now. We're claiming this as a victory for us and the sport."
The energy commission is considering whether to grant a license for the massive project to the Elsinore Valley Municipal Water District and its private partner on the project, The Nevada Hydro Company, of Vista.
Commission administrator Jim Fargo said from Washington, D.C., on Thursday that a revised plan for the 30-mile transmission line would bury a three-mile stretch along South Main Divide Road partway down a mountainside facing away from the lake.
Also to be put underground would be a stretch of power line connecting the main line to a powerhouse that would be built at the base of the mountain on the lake's side. That stretch would be more than a mile long.
The commission is no longer considering a previous plan to have the transmission line run above ground halfway down the mountain, Fargo, the federal administrator, said. The new route should answer the concerns of hang gliders who have said the line would prohibit them from gliding safely in certain areas, he added.
"It takes the project totally out of their way," he said.
While one local hang-gliding group hailed the latest development, another was more measured in its response.
Frank Hoffman of Elsinore Testing of Experimental Aircraft Mechanisms Inc. agreed that it's good that part of the line would be buried, but he said there are still plenty of concerns linked to the project.
Of particular concern, he said, is that the proposed powerhouse would be built in a location off Grand Avenue that is a prime launching site for hang gliders. He has been told the commission probably wouldn't allow a powerhouse on that site, but there have been no guarantees, Hoffman said.
"I'm happy to the extent that this issue may be settled," Hoffman said. "But I think there's more to do in the process. Certainly, the whole issue of the (powerhouse) is one that still remains."
Proponents of the project said they were pleased with the new proposed route of the transmission line.
Water board President Phil Williams said Thursday the new route ensures the line would not be built within a mile of the Horsethief Canyon community north of the city. The district has secured a guarantee from Nevada Hydro that if it were to go within a mile of the community, he said, that section would also go underground.
Elsinore Valley Municipal Water District board member Kris Anderson said that it is important to bury the part connecting the main line to the powerhouse.
Among the sites proposed for the powerhouse is a plot of land near Butterfield Elementary School and Anderson said that this should help quell concerns that the line would be harmful to children.
"That helps with that," she said.
Anderson also said she wasn't sure how the underground section of transmission line would affect the price tag for the project. A representative for Nevada Hydro could not provide that information Thursday.
Federal administrators have indicated in the past, however, that building the line underground would be extremely expensive. Fargo said it would cost about 10 times more to build the transmission line underground in the proposed segments than it would to do it above ground.
Williams said he thought the price tag would stay about $1.2 billion. Recent estimates had put the price tag for the project as low as $1 billion and as high as $1.3 billion.
Nevada Hydro, which is responsible for financing and building the project, has been able to cut costs in some areas, Williams said. Additionally, he said, prices for construction materials have dipped and that should keep the price in that range.
Germany-based Siemens has already signed on to build the transmission line and Williams said it would be employing new technology for burying high-voltage transmission lines. The company uses the technology in Europe, he said.
"For them, it's kind of like, 'We want to prove ourselves to the U.S.,'" he said. "If it works here in the U.S., it could open that market to them in the rest of country."
Thursday's news was the latest development in what has been a decade-long saga.
First proposed more than a decade ago, the Lake Elsinore Advanced Pumped Storage project calls for water pumped from the lake at night to be stored in a 100-acre reservoir behind a 180-foot dam in the hills southwest of Lake Elsinore.
The water would flow down the mountain toward the lake on summer days, when demand is at its peak, to energize electricity-producing turbines in a powerhouse built 300 feet underground. Water would be pumped back up the hill at night, when less electricity is needed and power costs less.
Linking the plant to the state power grid would be the 30-mile power line that would run partly through the Cleveland National Forest.
Community opinions on the project are split.
The proponents say it would have positive economic benefits by ensuring the lake is always full and providing up to 500 megawatts of much-needed electricity to the region. Opponents say the project would harm the environment, including the lake.
Opponent Chris Hyland, a water board member, said Thursday that this latest announcement is another attempt by the project's backers to make the project seem less of a danger to the community and environment.
Hyland, the only opponent on the water board, is facing re-election in November. She is one of three candidates opposed to the project running for the three seats that will open up at the end of the year.
Anderson and board member Ben Wicke are also seeking re-election.
Hyland sought to cast Thursday's announcement as an election-season ploy to garner support for the pro-project candidates. It's going to be impossible for the district and Nevada Hydro to get the financial backing for the underground transmission line, she said.
"This is election time and so Nevada Hydro has gone to them with this pie-in-the-sky story," she said.
Williams, who is not running for re-election, contended that neither the district nor Nevada Hydro had anything to do with federal officials deciding to pursue the underground line. He criticized Hyland for failing to acknowledge positive aspects to the project.
"She's got blinders on," Williams said. "She hates the project. She will die by that position."
Doug Pinnow, another anti-project candidate, said the underground section of the line only represents a small aspect of the overall project.
"There's so many other risks and problems with the community," he said. "This takes care of one little piece."
Contact staff writer Jose Carvajal at (951) 676-4315, Ext. 2624, or jcarvajal@californian.com.
More Stories
Advertisement
Kristan wrote on Oct 6, 2006 8:22 AM:I think it's the current board that has blinders on. The amount of money this project is going to spend is amazing. To say that the projected cost is only $1.2 BILLION and to state that it will stay the same when underground lines cost 10% more is ridiculous. Who ever has had a project come in under or even within budget. The Three Gorges Dam project was estimated at $25 billion and unofficially is around $100 billion. The Grand Coulee was estimated at $1.25 billion and actually cost $3.6 billion. There's another way to get San Diego their power without circumnavigating the California Public Utilities Commission process by add a pumping station that will lose millions each year. Don't let the underground lines fool you into thinking that this is now a golden project. It's rotten to the core.
johntherealtor wrote on Oct 6, 2006 8:24 AM:Isn't it interesting that the water board is agreeing to keep the above ground lines at least one mile away from Horse Thief Canyon because those homeowners have complained that the lines will devalue their property values, yet the board is happy with running the lines directly above the lower priced Lakeland Village homes. If more people knew how much these lines are going to lower their property values and destroy the natural beauty of Lake Elsinore by installing the huge metal towers and wires all the way along the side of the mountain, they would be doing everything possible to stop this project. Cutting out a short section for the hang glider is nice for them, but it still won't make any difference in the dramatic devaluing of home values that will result when the towers are installed. I just hope that the citizens vote in the opponents of this project and that the new water board will put the citizens first, not their personal financial gain and can prevent this disaster from happening.
Bob wrote on Oct 6, 2006 9:27 AM:Notice how incubents Ben Wicke and Christine Anderson could not find the time to attend the candidates forum a David A.Brown Middle school? We the citizens would have enjoyed hearing their positions on issues that ffect us in the district. If this LEAPS project is in fact so wonderful, why are the stakeholders of EVMWD having our money (2.3 million and going up) to promote this project? Answer: Someone is on the take or sells real estate in my opinion.
Analysis Paralysis wrote on Oct 6, 2006 10:20 AM:"Analysis Paralysis" is what the Chief of the US Forest Service said about his employees performances a few years ago. Then things started functioning in the direction of their initial credo: "SERVING THE LAND AND THE PEOPLE" The point I'm making here is that when an agecy is congressionally ordered to deal with an issue forced upon them by other agencies that they have to prioritize the LEAPS (special interest/investment) issue before serving at their initial job descriptions. The Cleveland National Forest is getting paid not to "serve the land" & the "users" of the forest! The EVMWD is mandating the USFS to manage their agency "pie-in-the-sky" affairs. There used to be numerous organized volunteer programs available on this forest that earned great sums in "in-kind" grants to help manage OUR PUBLIC LAND. The FS is so busy handcuffed in the board room that they cannot activly address volunteers can be doing next in the field. Hence, volunteer programs get shut out, areas get closed due to non-compliance, & there's a gate at every entrance to OUR PUBLIC LAND because of MANAGEMENT BY CONGRESSIONAL FORCLOSURE! WHAT CAME FIRST? THE LAND? THE PEOPLE? OR, THE UNWANTED PROJECT? sIEMENS CAN TAKE THEIR ROMAN TECHNOLOGY HYDRO-TOILET TO CHINA, MEXICO, OR AFRICA IF THEY WANT TO PROVE THEMSELVES OUTSIDE OF EUROPE. What we should be thinking about is this, "Who is getting paid, how much? To engage in the deadly sin of wasting valuable volunteer time?" Lastly, We would all like to see the contract as signed between EVMWD, Nevada Hydro, and Siemens as our public right under the Freedom Of Information Act and the application to the Army Corp of Engineers to wipe out an ecosystem. Remember! This is not private land! (I'm not some socialist quarry Nazi) We do have a say!
Bob wrote on Oct 6, 2006 11:08 AM:Phil Williams wrote: "She's got blinders on," Williams said. "She hates the project. She will die by that position." REPLY: So will her constituents...To bad your a Real Estate agents who will die selling the rest of us out for your own self interest.
DREAM EXTREME wrote on Oct 6, 2006 1:17 PM:YOU decide: Lake Elsinore for People or Industry, ALL or Nothing. Any version of the Project will destroy LE. Low tech, big, dirty, dusty during the 10years to complete. 3000 trucks each day blocking the Ortega Orange County Dream Extreme sports $'s we covit from our City. Are we a destination location or an industrial wasteland. Wind and Solar = more power less cost, little mess. The EVMWD web site promotes green power, to bad they don't read it.
Vote on Nov 7! wrote on Oct 8, 2006 12:23 AM:I'm glad to be reading all these comments and hope all of you tell 10+ friends and neighbors and those people tell 10 people to vote for Chris Hyland, John Lloyd and Doug Pinnow on Nov 7th. Those 3 are against LEAPS and are our only chance to stop this!
John wrote on Nov 17, 2007 9:52 AM:EVMWD and Nevada Hydro are scheming to make money off the taxpayers of this state and ratepayers of the local water district. The project will further erode the nature of the Cleveland National Forest along Lakeland Village and Wildomar with no benefit to those communities. EVMWD, a Lake Elsinore based agency has no qualms about constructing power towers, transmission lines, and the water transfer conduits which will scar and divide Lakeland Village. Cris Anderson stated the site near Butterfield Elementary is compatable with the proposed power plant because the power lines will be buried. I doubt the LEUSD will buy it and squash that site. I say STOP LEAPS and the malignent plan that threatens this community. I've lived here 28 years. It took 27 to get a signal light at the 74 HWY. and Grand Ave. intersection. That shows you what the commitment of Lake Elsinore is to the unincorporated areas on the SW side of the lake. The transmission line to San Diego failed to make it through the Pachanga "reservation" Casino and Temecula, but the scheme to connect through a more rural a less politcally connected area is now the Plan.
First name only. Comments including last names, contact addresses, e-mail addresses or phone numbers will be deleted. Attempts to misrepresent your identity or impersonate any person will not be approved. All comments are screened before they appear online, so please keep them brief. Comments reflect the views of those commenting and not necessarily those of the North County Times or its staff writers. Click here to view additional comment policies.