Feds favor hydro plant site near school

By: JOSE CARVAJAL - Staff Writer | Tuesday, January 30, 2007 11:32 PM PST

LAKE ELSINORE -- If a proposal to build a hydroelectric power plant southwest of the lake moves forward, the project's underground powerhouse should be built right next to Butterfield Elementary School, federal energy officials say in an environmental report released Tuesday.

That's not sitting well with Lake Elsinore Unified School District officials.

"A power plant right next to a school is probably not a good idea," district board member Kim Cousins said.

District officials already have said that if the site selected for the powerhouse ends up being near Butterfield Elementary, they will be asking the project's backers to build them a new campus elsewhere. If the powerhouse goes forward and that doesn't happen, the district could turn to the courts.

"They would have to find a site and replace Butterfield Elementary School," board president Tom Thomas said. "The district would bear no cost for the construction of and relocation to the new school."

As it considers whether to grant the project a license, the Federal Energy Regulatory Commission has been studying over the last couple of years potential locations for the project's three main components: the reservoir that would store water for the plant, an underground powerhouse that would generate electricity and a high-voltage transmission line that would link the project to the state power grid.

In its 600-plus-page report, commission staff recommend that a reservoir for the plant be built in Decker Canyon in the Cleveland National Forest and not in nearby Morrell Canyon, which was also being considered.

Commission staff also suggest that the 30-mile transmission line be built underground in one three-mile stretch and that other parts be built partway down the side of the hills facing the lake. The Elsinore Valley Municipal Water District and its private partner on the project, The Nevada Hydro Co., had been pushing for the transmission line to be built in a less visible area on the other side of the ridge.

But representatives of both said Tuesday that they were generally pleased with the report and the recommendations it makes.

"We're very comfortable with them," Nevada Hydro spokesman Chris Wysocki said. "There's nothing in this document that we're not excited about. ... We know where it's going now and we can begin the process of making sure this is built."

Powerhouse problems?

Water district board member Phil Williams has a different take. Though he is OK with many of the recommendations, he admitted he was troubled by the recommended site for the powerhouse.

"The biggest concern that we have is the school site," he said. "We need to be able to figure out some way around that. I'm not a proponent of that site by any means."

When they learned last year that the federal energy commission was eyeing land near Butterfield Elementary, school district officials raised questions about the appropriateness of the location. Construction of the powerhouse would create noise, dust and increased traffic on Grand Avenue that would not be conducive to learning, they said.

While the federal licensing process continues, the district must still wade through state environmental requirements. And Williams says that, as that process gets going, the district and Nevada Hydro might be able to convince the federal commission that the site is not suitable.

Building a brand-new school, which could cost more than $50 million, doesn't seem likely, he said.

"That is tremendously expensive," Williams said. "It would be a real problem for the project to bear that expense."

Wysocki, meanwhile, said that Nevada Hydro is willing to work with the district on finding a solution. He said that the state environmental process could turn up measures that would alleviate the impact on the school.

"We're very committed to working with the school district and we're very sensitive to any short-term impacts on the school site," Wysocki said. "We're willing to work with the district to identify any reasonable and feasible mitigation."

In recommending the site next to the school for the powerhouse, commission staff decided that the other location they were studying -- land to the northeast near where Grand Avenue meets Ortega Highway -- was too valuable a resource for hang gliders.

Gliders, who are said to come from all corners of the world to take advantage of the optimal conditions in the area, use that undeveloped spot as a landing zone. Their permit to glide in the area requires that they have a dedicated landing zone nearby.

The plan for that location had involved the creation of a formal landing zone for the hang gliders. Because construction of the powerhouse would place restrictions on landing there, according to the energy commission report, that plan was dropped.

But Ken Niemi of the Elsinore Hang Gliding Association said his group isn't necessarily opposed to locating the powerhouse on the land now used as a landing zone. The association is embroiled in a land dispute with a local developer over rights to the land and Niemi said that building the underground powerhouse there would help remedy that issue.

Niemi said that the water district, which has taken an interest in preserving hang gliding in the area, would obtain the land from the developer and could work with the association on creating a formal landing area there.

More visible power lines

The transmission line would be buried for several miles leading away from the powerhouse and would proceed above ground to electricity substations to the north and south. The line would come partway down the hills southwest of the lake and would be visible from almost anywhere in the valley.

Williams said that an important aspect of commission staff's recommendation is that the line would be built about a mile away from the Horsethief Canyon community just north of the city.

To the south, according to the report, the line would come closer to the La Cresta and Tenaja communities than the district and Nevada Hydro had initially proposed. Building the line deeper into the national forest away from those communities would pose a greater fire risk, according to the report, and would destroy untouched back-country areas of the forest.

Though pleased that a portion of the line would be buried, under the report's recommendations, Niemi said that the hang gliding association is still concerned about the sections of line that would be above ground.

Niemi noted that the line is buried only in a small area near the gliders' launching zone in the Cleveland National Forest. Gliders could still get caught in a line a little bit farther from that area, he said.

"Power lines and hang gliders just don't get along," Niemi said. "Even away from the launch, we can avoid them, but we still get nervous around them. We don't have an engine."

Chris Hyland, a former water district board member and a staunch opponent of the project, was critical of the commission Tuesday for going out of the way to accommodate hang gliders but failing to consider the concerns of residents opposed to the power lines.

Opponents have said that the transmission line would pose a fire risk and that its unappealing appearance would lower the values of nearby properties.

If part of the line can be built underground for the hang gliders, Hyland said, then the entire line should be buried to alleviate these concerns.

"Why are they going ... underground for them and not for the rest of the people," she asked. "Why are (the hang gliders) so privileged?"

Energy commission staff state in the report that they investigated the possibility but decided that it would be cost-prohibitive to bury the entire line.

The need for power

Williams and Wysocki both said they were particularly pleased to see in the report admissions from commission staff that the hydro plant and the transmission line would be energy assets to the region.

"... If licensed, the power from the project would be useful in meeting a part of the regional need for on-peak power," the report states.

Williams said that was a big admission from commission staff.

"What they've done is they said, 'OK, we think it should be a project,'" he said.

Opponents of the project, however, aren't so excited.

Like Hyland, current water district board member and hydro plant foe John Lloyd questioned the viability of the project based on an economic analysis included in the commission's report.

The project, if ultimately approved by the commission according to staff's recommendations, would cost about $1.3 billion to build. Also according to the report, the plant would cost $146 million a year to operate.

Because of that, Nevada Hydro has been seeking from the energy commission a guarantee that would ensure project backers would receive a 14.5 percent return on their investment.

And in the end, company executives have said, the project would lead to more than $200 million in energy savings to the state's electricity customers. So even though the project would lose money in operations, they have said, that would be offset by these benefits.

But Lloyd pointed out that the rate guarantee would mean the state's electricity customers would be picking up the tab for the annual operations costs.

"Somebody still has to pay it," he said. "It still doesn't mean it's a better value."

Critics such as Lloyd and Hyland will have plenty of opportunities to continue to register their concerns because there's still a long way to go in the process. Though the commission is expected to decide on the project this spring, there are still other hurdles it faces.

Williams said there are state and local requirements the project has to meet.

"This is a big milestone for the project," he said. "But it's not like it's going to get built next year. It's still got a ways to go."

Contact staff writer Jose Carvajal at (951) 676-4315, Ext. 2624, or jcarvajal@californian.com.

Next Previous
Bookmark and Share

Advertisement

Pre-Registration Comments[-]Go to Top

susan wrote on Jan 30, 2007 10:47 PM:Seems to me that peak power could be produced in a far less destructive and costly manner. Imagine how many houses could install insulation and solar panels for the estimated 1.3 BILLION dollar cost of this boondoggle project. Follow thel lmoney.

Joseph wrote on Jan 31, 2007 2:17 AM:The $200 million in electricity savings that Wysocki talks about is not going to bring dollars into the LEAPS income. It won't show up on the balance sheet or income statement as positive cash flow. This project will lose over $200 million per year, CAISO who gives the final say on the benefit amount to the state, has yet to say how much benefit there is to this facility and has reiteriated that any benefit isn't real dollars that LEAPS will ever receive either in cash or credit, it is simply a benefit, in other words something nice to have, but not cash in hand or an asset that can be depreciated. This project is a loser no matter how you slice it and no company will invest in it. This is why Wysoki has asked for CAISO to manage and operate this project, so they can be stuck with the huge financial losses. CAISO isn't so dumb as their last White Paper has shown, they won't take on the financial burden and debt of such a money losing project, and if a government agency won't take the project, a private company never will.

Excited wrote on Jan 31, 2007 9:14 AM:It is about time this project deserves the recognition as a necessity for the region, the state, and me as a resident of Lake Elsinore. I am just guessing but solar powers on everyone's house in Southern California? I think that would cost a little more. Just a guess though.

Leroy wrote on Jan 31, 2007 1:38 PM:In the LEAPS article, one thing that is being overlooked is the fact that the customers that would benefit from the power produced would be in the San Diego and areas to the south of San Diego - and not the customers in the Lake Elsinore area. Doesn't seem quite equitable - we have to plant detriment to our environment, cultivate chaotic construction, certain property devaluation and reap detrimental ramifications of risk of life, limb and property; others harvest the rewards (if the be any). Excited? "Recognition"? "Necessity for the region, state, and you as a resident of Lake Elsinore."? I guess you figured the electricity produced would flow to your meter. Guess again.

Eddie wrote on Jan 31, 2007 6:22 PM:Of course it would cost more to bury the entire distribution line but that should be a mandatory requirement for this project to go forward. If this were 1950 the available technology of the day would suggest power lines perched on towers, but in the world of today, buried utility lines are the norm for any new construction and this project in particular, should be held to that standard.

Informed wrote on Jan 31, 2007 7:36 PM:It never ceases to amaze me how ignorant and uniformned the general public is when making comments about public or private projects. First, if you really read the detail of the project, yes the rate payers pay for the funding of the project, but there is also an offset to your utility bill by reducing penalities for single source power (in some service areas) thereby actually reducing your overall bill. Second, how many of you would be screaming when the next energy crisis occurs and we have rolling blackouts and your ice cream, budweiser and hair dryers don't work??? California on average is closing more power plants than are being built and yet our population continues to increase. Where is this needed energy going to come from? Of course your typical response is - anywhere but in my backyard. Third, the threat of fire from the power lines is far less than any human or natural cause. Right now water for fire fighting in the Cleveland National Forest must come from helicopter or truck a significant distance away. Having the Decker Reservoir actually significantly reduces the amount of damage caused by fire by reducing travel time and provides a permanent source of water that the local community cannot or is not willing to pay for. If you want to build you house in the middle of nowhere then assume some of the risk. Forth, Lake Elsinore a eutrophic lake and by recyling the water which adds oxygen, and adding water from outside sources actually will significantly improve the health of a lake that is basically dead. Maybe now people will stop calling it Lake Smellsomemore. I could go on, but the majority of you won't make it this far. In short, if you want to bad mouth any construction project, I suggest you read the details and then form an opinion instead of being led around like a bunch of sheep. What happened our state and country that was so productive and prosperous?

Bessie wrote on Feb 1, 2007 10:53 AM:INFORMED what is your interest in the LEAPS project? Is it vested interest? Why are the hang gliders so naive to believe those power lines will really be above ground. The project people just want to shut the hang gliders up until they get approval of the project. Then the power lines will be above ground. Wake up people quit believing liars. I just attended a homeowners meeting in Horsethief Canyon and I could not believe the lies presented to the citizens. This project will destroy the value of our property. Horsethief homeowners better wake up and smell the roses. This project is not to benefit the people in this area it is for San Diego and Mexico and the lies and propaganda that we are being fed is unreal. Go And see where and how your rate money is spent. Right to keep Nevada Hydro in business cause they have no money and EVMWD is paying all their bills and have been since l997. The next election we need to change the water district leadership in Horsethief Canyon and parts of Lake Elsinore and now is time to start.

Registered Comments[-]Go to Top

Advertisement

Videos