ESCONDIDO: Palomar Pomerado pours concrete for new hospital

By ANDREA MOSS - Staff Writer | Wednesday, April 23, 2008 3:16 PM PDT

Construction crews pour concrete Wednesday for a new hospital that Palomar Pomerado Health is building in the Escondido Research and Technology Center in west Escondido. (WALDO NILO / Staff photographer)

ESCONDIDO ---- Dozens of trucks on Wednesday began delivering more than 4,000 cubic yards of concrete to the site where Palomar Pomerado Health is building a new hospital, marking a new phase in the $811.5 million project.


Watch A Video

The public hospital district broke ground on the project in September. Construction workers spent months installing underground utilities for the hospital and digging a gigantic hole that will become the foundation and basement for the towering structure.

The hospital is going up on 52 acres in the Escondido Research and Technology Center. When the 11-story building is finished, it will replace Palomar Medical Center in downtown Escondido as the public hospital district's flagship facility.

On Wednesday, cement trucks began showing up at the construction site's gate off Citracado Parkway around 7:30 a.m.

The vehicles were directed to the hole, where the wet concrete was fed through metal chutes and into wooden forms for the footings and the basement's walls.

"This is a big day for us," said Mike Samudio, a senior project manager for general contractor Rudolph and Sletten. "We've had some issues we've had to overcome. But we've overcome those issues, and we're moving on."

The steady stream of cement trucks was expected to continue until about 11 a.m. By then, Samudio said, 1,200 cubic yards of concrete ---- or enough to complete one wing of the basement ---- should have been delivered. The basement walls will be 18 inches to 24 inches thick, he said.

Repeat deliveries are scheduled to occur every two weeks through October, when more than 4,000 cubic yards of concrete will have been brought to the site. Samudio said the amount is enough to fill four or five football fields about 6 inches deep.

The concrete amount and the new hospital's 765,000-square-foot size make the project one of the biggest of its kind right now in the state, he said.

The state Office of Statewide Health Planning and Development signs off on all hospital construction projects in California. Patrick Sullivan, assistant director of legislative and public affairs for the agency, said there are hospitals in the works that will be bigger than the one Palomar Pomerado Health is building.

But the local facility, which the district is calling Palomar Medical Center West, may very well be the largest under construction now, he said.

"I don't know too many people who would question that one," Sullivan said.

By comparison, city building official Joe Russo said about 1,552 cubic yards of concrete went into the nearly completed parking structure for a new police and fire administration center the city is building on Centre City Parkway in northern Escondido. The center itself will require close to 3,000 cubic yards of concrete, he said.

Heavy rain this winter was one of the problems that slowed the new hospital project. Palomar Pomerado architect Mike Shanahan said he was thrilled to be at the point where concrete is being poured.

"You're getting me out of the ground," he said. "The minute you're out of the ground, you've got steel going up, so you can see everything. And you have a lot greater control over your job site. So it feels great."

The hospital's steel superstructure will start going up in August, officials said.

Contact staff writer Andrea Moss at (760) 739-6654 or amoss@nctimes.com.

Next

Advertisement

14 comment(s)[-]Go to Top

Question wrote on Apr 23, 2008 6:19 PM:"...it will replace Palomar Medical Center in downtown Escondido as the public hospital district's flagship facility."

What happens to the old hospital on Valley Parkway?

Gringo wrote on Apr 24, 2008 5:56 AM:Its gonnna be transformed into a retirement home/protein cracker factory.

To Question wrote on Apr 24, 2008 8:15 AM:Palomar Medical Center will remain as a hospital, but not as PPH's flagship facility. The $811 million only constructs 2/3's of the new hospital in the ERTC. PPH needs $300 to 500 million more to complete the missings parts. In the meantime, PPH's current plan to continue to use the downtown hospital's current Labor and Delivery facility, Emergency Room, etc., (until at least 2015). Whenever PPH is able to raise the additional $300+ million, it will then construct ERTC's missing Women's Center, Hospital Support Building, parking structures and complete the shelled portion (85,000 sq. feet) of the new hospital.

concerned wrote on Apr 24, 2008 11:08 AM:Great!!! broken old wheelchairs for the patients at palomer and 100+_k bonuses for the CEO?? how about showing some responsible spending at the hospital you already own...
Actions speak louder than words Mr Covert and Board.

aDAMANT wrote on Apr 24, 2008 11:13 AM:The old hospital will still be here but I think Gringo is right. We need more protein crackers in Escondido.

To Gringo wrote on Apr 24, 2008 1:07 PM:Dr. Rockso says you have seen Soilent Green to many times.

Karl wrote on Apr 24, 2008 1:34 PM:Why is the caption under the picture "Construction crews pour concrete Wednesday" when the picture shows a loader dropping dirt and rock into some kind of hopper?

Doesn't the NCT know the difference between dirt and concrete? Does the NCT now it's ..........................

Taxpayer wrote on Apr 24, 2008 3:42 PM:We would be wise to keep the current hospital in good working order until we can see whether or not PMC West and the power plant will be good neighbors. This is the question that most want to keep sweeping under the rug.

Kenneth wrote on Apr 24, 2008 5:27 PM:My wife had a kidney stone attack and was in agony, so we went to Palomar Hospital to their emergency room a few months back. It was a zoo. It was like a third world country. She began sobbing anew. I packed her back into the car and down we went to Kaiser Zion. We wonder what the new hospital will be like, and whether half to three quarters of the people in the ER will be on relief or even citizens. People who should have gone to a clinic with their stubbed toe or the sniffles or their drug overdose.

. million project. wrote on Apr 24, 2008 10:24 PM:WOW $811.5 million project ? This is a new number... I guess Mr. Mike's Traveling Miracle Medicine Show is going strong

Tina P wrote on Apr 24, 2008 10:31 PM:Pouring concrete Dropping dirt 'WHO CARES' if you think this is crazy look at our promises to Escondido.... LOL

Watch A Video wrote on Apr 24, 2008 10:35 PM:Heck! Let Wally play a DVD

Question wrote on Apr 25, 2008 5:42 PM:Gracias, "To Question" for the informative response. So, your understanding is that the 'old' (opened in 1966) hospital will serve as the center-city population's clinic (ER & baby stuff), while the 'new' place will be the real hospital, IF the money can be found to fund completion?

Q2: Besides the hospital, power plant & brewery up there on Citracado, are there any other businesses slated to build/open? I thought I read about a mall or something in the works.

WiseGuy wrote on Apr 29, 2008 9:29 AM:If they build it, I hope they dont come. We have too much work already at the downtown location. We are understaffed. I am looking forward to less patients at the new hosp. Thank you mr. covert if it results in a work load i can ALMOST keep up with. haha

First name only. Comments including last names, contact addresses, e-mail addresses or phone numbers will be deleted. Attempts to misrepresent your identity or impersonate any person will not be approved. All comments are screened before they appear online, so please keep them brief. Comments reflect the views of those commenting and not necessarily those of the North County Times or its staff writers. Click here to view additional comment policies.

Submit Comment[-]

(optional)
   

Advertisement

Videos